Exploring the Dashboard
Read-only demo loaded with a real-world urban metro project scenario.
Demo Project
Urban Corridor Infrastructure Project
Urban Metro ยท 23.4 km ยท 18 Stations ยท Health: D โ€” Delayed
๐Ÿ‘ Read-only ยท No inputs can be changed ยท โ† Back to website
Urban Corridor โ€” Sample Project
18%
Physical
+187d
Delay
0.77
CPI
D
Start
01 Apr 2024
Mobilisation
Baseline Finish
30 Sep 2027
Original contract
Forecast Finish
05 Apr 2028
โ–ฒ 187d slip
Data Date
14 Mar 2026
347d elapsed
BAC
โ‚น3,840 Cr
Sanctioned
Actual Cost
โ‚น892 Cr
Spent to date
Status
DELAYED
187d behind
Overall Progress
18%actual
Proj Setup
92%
Engineering
34%
Procurement
8%
Construction
0%
Scheduled %
74%
SPI
0.24
S-Curve โ€” Planned vs Actual & ETC
DD
โ” Planned โ•Œ Actual โ•Œ ETC Current โ•Œ ETC Recovery
Current Rate
Forecast 05 Apr 2028
Required SPI
1.47 to recover
EVM Metrics
PV
โ‚น2,842Cr
EV
โ‚น691Cr
AC
โ‚น892Cr
CPI
0.77
SPI
0.24
EAC
โ‚น4,987Cr
CV: โˆ’โ‚น201Cr ยท SV: โˆ’โ‚น2,151Cr ยท BAC: โ‚น3,840Cr
Contract Milestones 3/7
Project Brief & Scope
15 May 2024
Done
DPR Approval
20 Aug 2024
Done
Land Handover
10 Nov 2024
Done
Civil Contract Award
15 Feb 2026
At Risk
OHE & Traction Award
30 Mar 2026
Pending
Trial Run Start
01 Nov 2027
Pending
Data Date: 14 Mar 2026 ยท 134 Activities ยท 42 Critical ยท 18 Near-Critical ยท Baseline Active
All Phases โ— 42 Critical โœ“ Baseline โš  3 Neg Float
ActivityStatusRem Dur%FloatTimeline โ†’
โ–ผ PS โ€” Project Setup
Project Brief & Scope Conf.
Doneโ€”100%โˆ’6d
Design Brief & Tech Params
In Prog1.2w68%โˆ’4d
Land Survey & Boundary
Doneโ€”100%144d
โ–ผ ENG โ€” Engineering
Topographic Survey & LiDAR
Doneโ€”100%0d
Geotechnical Investigation
In Prog3.2w45%0d
Corridor & Prelim Alignment
In Prog4.8w28%4d
Foundation Type Selection
Not Started6.2w0%โˆ’2d
โ–ผ PROC โ€” Procurement
Structures Tender Documents
Not Started10.4w0%0d
Structures Bidding & Award
Not Started14.2w0%0d
โ–ผ T&C โ€” Testing & Commissioning
Integrated System Test
Not Started8.0w0%0d
Trial Run & CMRS Inspection
Not Started6.0w0%0d
Total Design Hours
18 stations ยท 23.4 km ยท 2,847 hrs/km
66,620
Core Inputs
Metro
Preliminary Design
23.4
18
India
Read-only demo. Full version has editable inputs that recompute instantly.
Effort by Discipline
Alignment & Civil
17,480
Structures
13,640
OHE / Electrification
9,620
Track Design
7,380
Survey & Geotech
5,940
Signalling & Telecoms
4,880
Architecture
3,860
Grade Split
Director
6,662
10% ยท โ‚น56.6L/yr
Senior
17,985
27% ยท โ‚น115.4L/yr
Mid-Senior
24,189
36% ยท โ‚น130.8L/yr
Junior
17,784
27% ยท โ‚น72.1L/yr
Schedule Intelligence ยท Last computed: 14 Mar 2026 23:14 ยท 134 activities ยท 42 critical ยท 18 near-critical
โš  3 activities with negative float โ€” schedule is infeasible
โš  Critical density 31% โ€” schedule fragile
โš  18 near-critical activities within 5% of total float
โ—‰ Procurement on critical path โ€” 2 long-lead items at risk
๐Ÿ”— 12 activities with no successors โ€” logic may be incomplete
Immediate Action
Infeasible Constraints โ€” 3 Activities with Negative Float
"Project Brief & Scope" โˆ’6d float. "Design Brief" โˆ’4d. "Foundation Type Selection" โˆ’2d. Late finish earlier than early finish โ€” predecessors, constraints or durations in conflict.
Recommended: Review predecessor chain and constraints. Remove hard constraint if not contractually required, reduce duration, or introduce SS lag.
Risk Watch โ€” 31% Critical
Critical Density Dangerously High
42 of 134 activities (31%) on critical path. Very low redundancy โ€” delays cascade simultaneously. Target: <20% critical density.
Recommended: Identify top 3 critical activities for duration reduction. Add 2-week buffer milestones between Engineering and Procurement.
Grab Opportunity
High-Float Activities for Resource Reallocation
Archaeological & Heritage NOC (144d float), Railway & Road Crossings (128d), Forest & Wildlife Clearance (112d) โ€” resources can be redeployed to accelerate the critical path.
SPI โ€” Latest
0.24
โ†“ Declining ยท Was 0.31
Delay
+187d
โ†‘ +24d since last period
Progress
18%
vs 74% planned ยท โˆ’56%
Trend
Deteriorating
SPI falling ยท delay growing
โšก Trend Analysis
SPI declined 0.31โ†’0.24 (โˆ’0.07) over 6 periods. Delay accumulating at 31 days/period. At current rate forecast extends to April 2028 โ€” 187 days beyond contract. 3 activities with negative float require immediate resolution.
SPI Over Time
SPI 1.0 0.24
Delay Accumulation (days)
42d 187d
Progress Heatmap โ€” Phase by Period
PhaseMay '25Jul '25Sep '25Nov '25Jan '26Mar '26SPIStatus
Project Setup0.980.940.910.880.820.790.79Behind
Engineering0.880.780.680.580.540.510.51Critical
Procurement0.920.740.630.550.480.440.44Critical
ConstructionNot yet startedโ€”โ€”Pending
T&CNot yet startedโ€”Pending
Schedule Narrative
Auto-generated from CPM data ยท 14 Mar 2026
18% Physical+187d DelayHealth: D
๐Ÿ“‹
Programme Status
Section 1 of 5 ยท Auto-generated
As of 14 March 2026, physical progress is 18% against a scheduled target of 74% โ€” a variance of โˆ’56 percentage points. Forecast finish 05 April 2028 represents a slip of 187 days against baseline 30 September 2027. SPI: 0.24. Health: D โ€” Critically Behind.
"At current trajectory the project will not achieve baseline. Immediate and sustained intervention required across Engineering and Procurement."
๐Ÿ”ด
Critical Path Analysis
Section 2 of 5 ยท Auto-generated
42 activities on the critical path (31% of programme). Leading: PS.CI.01 Project Brief & Scope, ENG.GI.01 Geotechnical Investigation, ENG.CV.01 Corridor Alignment, PROC.CV.01 Structures Tender Documents, and 38 more. 3 activities have negative float โ€” immediate recovery action required.
๐ŸŸก
Near-Critical Activities
Section 3 of 5 ยท Auto-generated
ENG.CV.03 Corridor & Preliminary Alignment (float: 4d), ENG.CV.04 Detailed Alignment (float: 4d), ENG.DR.01 Drainage Works (float: 6d) โ€” any delay directly impacts completion. 18 activities require weekly monitoring.
๐ŸŸข
Schedule Flexibility
Section 4 of 5 ยท Auto-generated
High-float resources available for reallocation: PS.PE.04 Archaeological NOC (144d), PS.PE.05 Road Crossing Permissions (128d), PS.PE.03 Forest Clearance (112d) โ€” redeploy to accelerate critical path.
๐Ÿ“Š
Phase-by-Phase Summary
Section 5 of 5 ยท Auto-generated
Project Setup: 92% complete (14 of 18 critical) โ€” 3 neg float. Engineering: 34% (16 of 42 critical) โ€” SPI 0.51, significantly behind. Procurement: 8% (8 of 24 critical) โ€” long-lead items critical. Construction: 0% not started. T&C: 0% not started โ€” entire phase on critical path, zero buffer.